Roadbridge tasked AmmLee Group International to remove defective concrete from the base of a wind turbine with hydrodemolition.
Challenge
Roadbridge had discovered that the wind farm project they had been contracted to build had defective concrete on the base of the wind turbine. AmmLee Group were asked to find the areas of defective concrete and safely remove the concrete with hydrodemolition.
Solution
AmmLee Group identified the defective concrete areas (6m³) and safely removed the concrete using hydrodemolition at 2800 pressure.
Result
Ammlee Group successfully removed the 6m³ defective concrete in 5 x 10-hour shifts, allowing Roadbridge to replace it.
Project details
Client: Roadbridge: One of Ireland's leading civil engineering companies
Location: Ireland
Timeframe: 5 days
Related Projects
Talk to us about your Project
If you would like to discuss how our services would work for one of your projects, please get in touch. One of our technicians will be happy to talk you through our processes and how we would approach your job. In addition to advising you, we will also be able to provide a no-obligation quote for the work. To talk about your project, call us on N.Ireland 028 9346 2778 or London 020 7101 3191.