Staffordshire

Manual Hydrodemoltion

Case Study


Project details

Client: NDA agreement

Location: Staffordshire, West Midlands of England

Timeframe: Completed in 20 hours split between two 10 hour shifts removing a total of 3 cubic meters of concrete

Service provided: Manual Hydrodemolition using a Hammelmann HDP144

Project background

We received a call from the client who urgently needed our expertise as the current hydro demolition company was unable to successfully complete the project and needed finished immediately.

Challenges

The client site had no water on-site, we successfully overcame this challenge by transporting 30,000 litres of water in order to complete the project. 

Result

We removed a total of 3 cubic meters of concrete in 20 hours across two 10 hour shifts. The client was extremely happy and used our services a week later on the same site.

If you would like to hire Ammlee for hydrodemolition services, please get in touch for a Free, No Obligation Quote.

GET A QUOTE

Related Projects

Talk to us about your Project

If you would like to hire Ammlee for hydrodemolition services, please get in touch for a Free, No-Obligation Quote.

Contact US
Share by: