Surrey Hydrodemolition Case Study


Ammlee Group International was tasked with carrying out Robotic Hydrodemolition to the beam to full depth up to the face of the Column/intersecting beam the total area to be removed was 9m³. Time to complete was 8 days.

Challenge

Carrying out the hydrodemolition safely and HAVS free.

Solution

Robotic Hydro demolition using the Falch Multi worker at 2500 bar 22lpm

Result

The project was completed a day early and to the clients satisfaction.

Project details

Client: NDA

Services provided: Robotic Hydrodemolition

Location: Epsom Surrey, United Kingdom

Timeframe: 8 days